Pangnirtung Wastewater Plant Roofing Assessment

N/A

4 months

$200,000

N/A

Background

Concentric was retained to assess and investigate extensive wind damage to the roof and exterior walls of this wastewater treatment plant. The assessment and subsequent investigation and analysis concluded that the roof assembly was not structurally adequate to resist the local wind pressures and gust effects.

Approach & Methodology

The owner retained Concentric to provide full re-design and construction review services. Because the facility had to remain in operation during the repairs, the repair program had to be as non-intrusive as possible.

Concentric developed a workable solution that was able to re-use the existing steel deck and therefore required minimal disruption to plant operations. All new materials had to be airlifted in, which required a significant logistical effort and no margin for error in the design.

Key Challenges

The bulk of the work was completed in the month of December under challenging weather conditions.

Key Personnel

Project Director & Manager: Allan Murray, P. Eng.

 

Structural Assessment

Contact Concentric

If you would like to speak to someone about your next project, fill out the form or contact one of our offices by phone.